SouthGate Constructors will be closing O’Connor Boulevard under SH 114 May 8 through 14 for initial bridge removal work for the Midtown Express Project:
- Dates and Times: 9 p.m. May 8 to 5 p.m. May 9.
Full closure. All lanes of north and southbound O’Connor Blvd. will be closed under SH 114. Detour routes will be posted.
Work Performed: Initial bridge removals.
- Dates and Times: 9 p.m. to 9 a.m. May 9; 9 p.m. to 6 a.m. May 10 and May 11.
Full closure. Northbound O’Connor Blvd. under SH 114 will be closed. Please use the frontage roads to Wingren Rd. for detour.
Work Performed: Initial bridge removals - Dates and Times: 9 p.m. to 9 a.m. May 12 through May 14.
Full closure. Southbound O’Connor Blvd. under SH 114 will be closed. Please use the frontage roads to Hidden Ridge for detour.
Work Performed: Initial bridge removals